Method Statement For Installation Of Air Handling Unit
Care must be taken to ensure that the actuator does not attempt to push the damper beyond fully open or fully closed positions.PROJECT NAME METHOD STATEMENT FOR INSTALLATION OF AIR HANDLING UNITS & FRESH AIR HANDLING UNITS Ref. Depending on the ambient temperature and plant location. Pipe connections and valve arrangement must be checked. Works Method Statement. Works Type: Installation of Mechanical and Electrical Equipment. Descargar Microsoft Office 2003 Gratis Completo Para Windows Vista. Dust or waste material cannot escape the units and enter into.
Advertisement • Fork Lift or Crane with capacity & arrangement in line with the Manufacturer’s recommendations, pallet mover and as required at site. • Hydraulic Trolley • Portable hand tools. • Portable Drilling Machine/ Grinding Machine & Angle Cutter.

• Spirit Level / Level Threads • Scaffolding with platform. Material Handling & Storage On receipt of the Air Handling Units and accessories at site, necessary precautions shall be taken for unloading, shifting & storage, as follows:- • All Air Handling Unit received at site shall be inspected and ensured that the materials are as per approved material submittals in terms of their make, model type, point of origin and capacity. • Upon arrival at site, the Air Handling Unit shall be off-loaded carefully at site by the Site Engineer / Site Supervisor using necessary manpower and required equipment to ensure that no damage is caused to the Air Handling Units.
• At site all the Air Handling Units will be stored in a clean / dry place and adequate covering by tarpaulin sheets will be done to protect the equipment from deposition of construction dust till it is finally shifted to its location. • Any discrepancies, damage etc., found will be notified and reported for further action suitably. GENERAL INSTALLATION REQUIREMENTS • Ensure that the proper clearance is available from civil side before commencement of works. • Ensure that the work area is clean and safe for carrying out the activities. • Prior to start of works, it shall be ensured that the relevant shop drawings and coordination drawings are approved and issued for construction. • It shall be ensured that no contradiction with other previously installed services, and if there is any shall be cleared. • It shall be ensured that the material issued is as per the approved material submittal.
INSTALLATION PROCEDURE FOR AIR HANDLING UNIT AHU’s • The following procedure shall be followed for the installation of Air Handling Units. • Visually inspect the exterior casing of the Air Handling Units for any damages during transporting and transferring of the units.
• Materials shall be submitted for Consultant approval before proceeding with installation. • Cut all banding (if applicable) loose from skid but do not remove the skids until the unit is shifted to the installation area. • Site Engineer shall ensure that the installation of the Air Handling Unit is carried out in accordance with manufacturer’s installation recommendations and specification. • Prior to start of installation, refer to the approved shop drawing related to the area of installation and ensure that required material is available at site as per approved material submittals. Full Spectrum Warrior Ten Hammers No Cd Crack there. • Ensure that the equipment and accessories are stored properly and there is no damage or deformity of any kind during transportation of material from site store to the working area. • After inspecting the work area, ensure that it is totally ready for installation. Then the required equipment shall be moved to the place of installation.